Pipes For Perth (Water Corporation) Works Commenced

Published on Tuesday, 11 January 2022 at 8:00:00 AM

Water Corporation has commenced pipe works in East Fremantle.

Their authorised contractor, DM Civil, has begun work to renew water pipes in East Fremantle as well as those in adjacent suburbs of Bicton and Palmyra.

Details of the new water pipe alignment are included below.

map pipes for perth

When is this happening?

Service locating will be completed from Monday 22 November to Friday 17 December 2021. This work will be completed between 7am and 5pm on weekdays.

Location Estimated timing (subject to change)
Fletcher St, between Moss St and Petra St Monday 22 November to Tuesday 30 November 2021
Petra St, between Fletcher St and Canning Hwy Wednesday 1 December to Monday 6 December 2021
 Petra St, between Canning Hwy and Fraser St Tuesday 7 December to Thursday 9 December 2021
Fraser St, between Penshurst St and Petra St Friday 10 December to Tuesday 14 December 2021
George St, between Silas St and Moss St Thursday 16 December to Friday 17 December 2021
Moss St, between George St and Fletcher St Wednesday 15 December 2021
Silas St, between Saint Peters Rd and George St Monday 10 January to Tuesday 11 January 2022
Saint Peters Rd, between Sewell St and Silas St Wednesday 12 January to Friday 14 January 2022
Sewell St, between Canning Hwy and Saint Peters Rd Monday 17 January 2022

No work is planned over the festive break from 18 December 2021 to 9 January 2022.

Construction work to install the new pipe is expected to begin on Monday 10 January 2022 and be completed in a staged approach through to late 2022.

More information about staging and estimated timeframes will be provided by Water Corporation in the coming weeks.

What will the impacts be?

Service locating involves drilling small potholes into the road along the alignment to locate existing underground services such as telecommunications, gas pipes etc.

During the work, residents may notice more noise, dust and vibrations.

Potholes will be temporarily reinstated once work is complete.

Traffic management personnel will be on site to safely assist drivers around the work area.

We understand our work may cause temporary inconveniences and are committed to working with you to minimise impacts.

Want to know more?

For more information about the project, visit ‘Pipes for East Fremantle’.

If you need to report a fault, emergency or security issue, please call 13 13 75 (24 hours)

Back to All News