Roadwork Program 2017

Published: Thursday, 9 November 2017 at 5:15:42 PM

Council has engaged Industrial Roadpavers (WA) Pty Ltd to undertake asphalt works to various streets within the Town. 

Residents are assured the contractors will make every effort to keep any disruption to a minimum.  Construction works will be carried out between 7am and 5pm each day and roads will be available to use immediately after installation.

For further information please contact either Clint Skewes from Industrial Roadpavers on 0418 934 700 or Council's Operations Manager Steve Gallaugher on 0400 082 291.

See below program of works:

Streets

Duration

Date

George St (Moss to Bedford)

Moss St (George to Fletcher)

One day

4 December 2017

Fletcher St

Two days

5 & 6 December 2017

Easton St

One day

7 December 2017

View Tce

One day

8 December 2017

Clayton St

One & half days

11 & 12 December 2017

Woodhouse Rd

One & half days

12 & 13 December 2017

Munro St

One & half days

14 & 15 December 2017

Wolsely Rd

One day

18 December 2017

King St

Two days

19 & 20 December 2017