TOWN OF EAST FREMANTLE FOOTPATH PROGRAM

The has engaged J&M Asphalt to undertake our footpath program for this year.

See below for the program.

If you have any queries, please contact the Town on (08) 9339 9339 or email admin@eastfremantle.wa.gov.au 

STREET

 

START – Week Commencing

DURATION

 

Resurfacing

 

 

Windsor Road

Canning to Fraser – Western Side

6 November

5-8 Days

Walter Street

Canning to Fraser – Western Side

13 November

5-8 Days

Oakover Street

Millenden to Canning – Western Side

20 November

5-8 Days

Fortescue Street

Marmion to Fletcher – Northern Side

28 November

5-8 Days

Allen Street

Marmion to Fletcher – Eastern side (322m)

4 December

5-8 Days

Marmion Street

Hubble to Sewell – Northern Side

11 December

3-5 Days

St Peters Road

Sewell to King – Southern Side

11 December

2-3 Days

 

Reconstruction

 

 

Canning Highway

Town Centre to Old Post Office

Waiting on Main Roads Approval

TBA

Petra Street 

Fraser to View – Western Side 30 October 5-8 Days