Updated - TOWN OF EAST FREMANTLE FOOTPATH PROGRAM 2018

The Town has engaged J&M Asphalt to undertake our footpath program for this year.

See below for the updated program for 2018.

If you have any queries, please contact the Town on (08) 9339 9339 or email admin@eastfremantle.wa.gov.au 

STREET

 

START – Week Commencing

Approx. Completion Date

 

Resurfacing

 

 

Walter Street

Canning to Fraser – Western Side

13 December 2017

19 January 2018

Oakover Street

Millenden to Canning – Western Side

9 January 2018

19 January 2018

Fortescue Street

Marmion to Fletcher – Northern Side

23 January 2018

13 February 2018

Allen Street

Marmion to Fletcher – Eastern side (322m)

6 February 2018

27 February 2018

Marmion Street

Hubble to Sewell – Northern Side

20 February 2018

28 February 2018

 

Reconstruction

 

 

Canning Highway

Town Centre to Old Post Office

Waiting on Main Roads Approval

TBA